Budget and Schedule

Table 6-1 Budget
Table 6-2 Schedule

The project was budgeted at $500 with actual project cost coming in under $200.

 

Use of rapid prototyping with the 3D Printer significantly reduced project cost when compared to other methods of manufacture.

The schedule called for 146 hours of work with actual time spent being estimated within 30 hours behind schedule.